UPRR 24-Inch Sewer Interceptor Phase 3 (P1930-20)

Project Description

The rehabilitation effort includes approximately 3,173 linear feet using trench less rehabilitation techniques (CIPP thermally cured or UV cured). The project also includes approximately 3,600 linear feet of temporary sewer by-pass pumping. 

Important Dates

Start Date:
August 2020
Estimated End Date:
October 2020
Funding Source:
Water and Sewer Fund
Estimated Cost:
$749,014.00


Project Contacts

P1930 Contacts


Status

None at this time.